| Road Maintenance |
The Neighborhood has voted at the general meeting to a 5 year
special assessment to all homes / lots on paved lower Mt Royal
roads of $60.00 to cover increased road maintenance. |
Fall 2014 |
$123,000.00 form increased road dues over five years. |
General Meeting
Presentation GWE Report V
3.0
Completed Projects |
| Ditching Project |
Polvadera ditching will be completed from Ridgemont to Sleath road. |
Completed - Fall 2008 |
$12,000.00 - Approved by the general membership meeting 2008 |
Polvadera Ditching Pictures |
| Road repairs |
Major Damage to Polvadera road at Creedmoor and west of Camileta
will require major repair |
Spring 2008 |
$5,800.00 - Approved by the general membership 2008 |
|
| Street Sign |
We usually need to replace 5 to 20 signs per year due to vandals or
vehicles knocking them down. |
Never ending |
$500.00 per year - Road Fund |
New
Signs |
| Security Camera's |
Vandals have been damaging the beach equipment and non residents
have been trespassing. |
Fall 2007 |
$2,500.00 Approved / General Fund |
Completed Fall 2007 |
| Repair beach gate |
Beach gate will not close on it's own allowing people to enter with
out keys. |
Completed - Spring 2007 |
$500.00 / Beach fund |
No funds - temp repaired |
| Repair concrete under pavilion |
Cut concrete around the base of columns, jack up roof to
straighten and reset footings |
North side complete 2011 |
$need total |
South side due to be complete
2012 |
| Repair Roof at Beach |
Shingles missing from beach pavilion roof |
Completed - Spring 2007 |
$ No Total Yet / Beach fund |
Done during Beach Clean Up 2007 |
| Polvadera Ditch |
Re-Ditching and replacing undersized culverts along the south side
of Poladera |
Completed - Sept 2005 |
$30,000.00 / Mt Royal General Fund, $4,000.00 / Road Fund |
Winning Bid /
Pictures |
| Web Site |
Permanent Neighborhood Web Site |
Completed - July 2005 |
$500.00 / Mt Royal General Fund |
|
| Speed Humps |
Install up to 14 speed humps through out lower Mt. Royal |
Completed -September 2006 |
$500.00 per hump / Road Fund |
Heidi's presentation |
| Bridge Replace / Repair |
Replace Polvadera Bridge & repair Creedmoor bridge. |
Completed Oct 2005 |
$495,000.00 / S.A.D Complete Subdivision |
Letter From
Bob Husak Construction
Pictures |
| Sanitary Sewers |
Install pressure sanitary sewers on Creedmoor, Polvadera
(part), Camelina, Sherbrooke And Ridgemont (Part). |
Completed - 2000 |
$3,500.00 per lot in the S.A.D |
|
| Beach Barn |
Old fashion barn raising down at the beach. |
Completed - 20?? |
$1,200.00 / Beach Fund |
Beach Barn |
| Road Paving |
Pave lower Mt. Royal roads & install storm drains |
Completed - 19XX? |
$4,500.00 per lot in the S.A.D (average) |
|